Our projects
Моделирование металлических конструкций в AVEVA
The Customer: АО «Полиметалл» Execution period: ноябрь 2021 г. — февраль 2022 г.
Work on adjusting the project documentation for the project: «Substation 220 kV Stroitelnaya»
The Customer: NIPIGAZ AO (JSC) Execution period: December, 2014 — December, 2016
Complex of works on the capital construction project of the Amur Gas Chemical Complex. Substation 500 kV AGHK
The Customer: NIPIGAZ AO (JSC) Execution period: December, 2014 — December, 2016
Complex of works on the project: «Construction of the 220 kV Ozernaya substation with two autotransformers 125 MVA each and 110 kV switchgear, construction of the 220 kV Chita - Ozernaya I and II circuits with an approximate length of 230 km, reconstruction of the 220 kV Chita substation»
The Customer: Ozernoye OOO (Ltd.) Execution period: July, 2020 - July, 2021
Complex of works on the project: «Construction of the 35/6 kV substation GOK and the branch OHTL 35 kV from the 35 kV overhead line Sosnovo-Ozerskaya-Gunda to the 35/6 kV substation GOK»
The Customer: Ozernoye OOO (Ltd.) Execution period: April, 2020 - February, 2021
Комплекс работ по разработке проектной документации по объектам: ЛЭП 220 кВ Таежная-Малмыж, ПС 220 кВ Малмыж и ПС 500 кВ Таежная
The Customer: «Amur Minerals» OOO (Ltd.) Execution period: April, 2020 - 2021
Execution of a complex of works on the project: «OHTL 220 kV Oznachennoe - Stepnaya (section from support 64 to the substation 220 kV Stepnaya) and the substation 220 kV Stepnaya with incoming lines 220 kV, Askiz, Republic of Khakassia»
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: March, 2020 - 2021
Implementation of a complex of works on the investment project: «Construction of the second 220 kV OHTL Minusinskaya master station - Kamala-1 with an approximate length of 445 km»
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: December, 2020.
Implementation of the project: «Construction of a refueling complex of JSC AERO-Sheremetyevo»
The Customer: «AERO-Sheremetyevo» AO (JSC) Execution period: June, 2020 - January, 2021
«Upgrading of Izhevskaya CHPP-2»
The Customer: «ROTEK» AO (JSC) Execution period: September, 2020 - 2021
Implementation of a complex of works on the project: «Construction of waste water treatment facilities with sewerage networks in the villages of Termalny and Paratunka, Yelizovsky district of Kamchatka Territory» 2nd start-up complex
The Customer: Teplo Zemli АО (JSC) Execution period: March, 2020 - February, 2021
Implementation of a complex of works on the project: «Substation 110/10 kV «SEZ Yelets 1» on the territory of SEZ «Lipetsk» in the Yeletsk district of the Lipetsk region»
The Customer: JSC «SEZ PPT «Lipetsk» Execution period: 17 November, 2020.
Project for the construction of the mine «Inaglinskaya», Inaglinsky GOK AO (JSC). Construction of the substation «Severnaya» 35/6 kV with incoming lines 35 kV (Kolmar OOO (Ltd.))
The Customer: Inaglinsky GOK AO (JSC) Execution period: January, 2021
Development of project documentation on the project: Gas Treatment Plant in the area of Ust-Luga settlement. Power distribution station 110 kV
The Customer: NIPIGAZ AO (JSC) Execution period: February, 2021.
Development of work documentation for the facilities: Substation 500 kV; OHTL 110 kV Amursky Gas Chemical Combine-MSDS-1; OHTL 110 kV Amursky Gas Chemical Combine - MSDS -2; OHTL 110 kV Amursky Gas Chemical Combine - MSDS-3; Substation 110 kV MSDS -1; Substation 110 kV MSDS -2; Substation 110 kV MSDS -3 on the Project: Amursky Gas Chemical Combine
The Customer: NIPIGAZ AO (JSC) Execution period: July, 2020 - October, 2021
Comprehensive reconstruction of substation 220 kV Zapadno-Sibirskaya
The Customer: Branch of CIUS EES АО (JSC) — CIUS of Siberia (CIUS Sibiri) Execution period: April, 2017 - 2021
Implementation of a complex of works on the project: «Construction of sewage treatment facilities with sewerage networks in the villages of Termalny and Paratunka, Elizovsky District, Kamchatka Territory»
The Customer: Teplo Zemli АО (JSC) Execution period: March, 2019 - November, 2020
Development of project documentation for the reconstruction of the heat supply source of Baikalsk town (Irkutskaya Oblast, Slyudyansky district, the premises of Baikalskaya CHPP), Stage-I
The Customer: Administration of Baikalsk municipal settlement Execution period: December, 2018 – June, 2020
Implementation of a set of work in progress on the project: «Construction of 220 kV Sukhoi Log substation with a transformer capacity of 126 MVA, construction of a single-circuit 220 kV overhead line Peleduy - Sukhoi Log with an approximate length of 248 km, construction of two single-circuit 220 kV overhead lines Sukhoi Log - Mamakan with an approximate length of 169.9 km each»
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: May, 2019 — April, 2020
Comprehensive upgrading, retooling and reconstruction of the 500 kV substation Beskudnikovo for the needs of the branch of «FGC UES" PAO (JSC) - MES of the Center»
The Customer: FGS UES PAO (JSC) – Main Power Networks of the Centre (MES Centra) Execution period: December, 2018 – March, 2020
Complex of works on 6, 8 10 stages on the project: «Reconstruction of the 220 kV Kalininskaya Substation»
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: January, 2020 - July, 2021
Novy Port gas and oil field. Engineering services
The Customer: GiprotyumenNeftegaz PAO (JSC) Execution period: February, 2020 - August, 2021
Construction of the 2nd OHTL 220 kV Minusinskaya master substation — Kamala-1, appr. length = 445 km.
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: November, 2019 — December, 2019
Execution of survey and design works for the construction of a 110 kV transmission line for connecting the substation of the Kamenskaya Wind Farm and the substation of the Sulinskaya Wind Farm to electrical networks within the construction project: «Kamensko-Krasnosulinskaya Wind Farm-Severnaya site» (VetroPark)
The Customer: The 2nd Wind Farm - Fund for Wind Power Engineering Development ООО (Ltd.) Execution period: April, 2019 — December, 2019
«OHTL 220 kV Peleduy - Sukhoi Log, OHTL 220 kV Mamakan - Sukhoi Log with substation 220 kV Sukhoi Log» OHTL 220 kV Mamakan-Sukhoi Log
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: June, 2018 – July, 2019
Substation 220 kV Zharki, OHTL 220 kV and reconstruction of Substation Novo-Krasnoyarskaya-220 kV to be renamed into Substation 220 kV Zharki. Amendments to work documentation
The Customer: Branch of CIUS EES АО (JSC) — CIUS of Siberia (CIUS Sibiri) Execution period: April, 2017 — August, 2019
Novy Port gas and oil field. Engineering services
The Customer: GiprotyumenNeftegaz PAO (JSC) Execution period: April, 2019 — January, 2020
Design of security zones on the project: «OHTL 220 kV Peleduy-Sukhoi Log, OHTL 220 kV Mamakan - Sukhoy Log with substation 220 kV Sukhoi Log». Working documentation
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: September, 2018 — November, 2018
«OHTL 220 kV Peleduy - Sukhoi Log, OHTL 220 kV Mamakan - Sukhoi Log with substation 220 kV Sukhoi Log» Substation 220 kV Sukhoi Log COMPLEX 1. Working documentation
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: April, 2018 — October, 2018
Novy Port oil and gas field. Substation 110/6 kV PSP, Substation 110/10 kV, Substation 110/35 kV (gas-turbine power plant)
The Customer: GazpromNeft Novy Port ООО (Ltd.) Execution period: December, 2017 — December, 2018
OHTL 500 kV Voskhod - Vityaz
The Customer: Branch of CIUS EES АО (JSC) — CIUS of Siberia (CIUS Sibiri) Execution period: December, 2017 — January, 2018
«500 kV overhead line Rostovskaya NPP-Rostovskaya with the expansion of the 500 kV Rostovskaya substation (one 500 kV line cell). Amendments». Development of working documentation, field supervision
The Customer: FGS UES PAO (JSC) – Main Power Networks of the South (MES Yuga) Execution period: June, 2017 — February, 2018
Reconstruction of MSDS-220 (main step-down substation 220 kV) on the premises of the operating plant GazpromNeft-ONPZ АО (JSC)
The Customer: GazpromNeft0ONPZ АО (JSC) Execution period: April, 2016 — June, 2018
OHTL 220 kV Selikhino — Vanino with the installation of the 2nd Auto Transformer АТ on Substation 220 kV Vanino on the project: OHTL 220 kV Komsomolskaya – Sovietskaya Gavan’ (renamed on the basis of positive findings of Glavgosexpertiza of Russia into: OHTL 220 kV Komsomolskaya – Selikhino – Vanino)
The Customer: FGS UES PAO (JSC) – Main Power Networks of the East (MES Vostoka) Execution period: June, 2016 — December, 2018
Comprehensive technical upgrading and retooling of Substation 220 kV Levoberezhnaya (amendments)
The Customer: FGS UES АО (JSC) — Branch of CIUS EES ОАО (JSC)-CIUS of Siberia Execution period: January, 2016 - December, 2017
Reconstruction of 110 kV Switchgear within the project: Reconstruction of Substation 500 kV Tyumen
The Customer: FGS UES PAO (JSC) – Main Power Networks of Western Siberia (MES Zapadnoy Sibiri) Execution period: March, 2017 — September, 2017
Technical retooling of Substation 110 kV Evikhon for the project: Development of Vadelypsky oil and gas field. OHTL 35 kV connecting Substation Evikhon 110/ 35/ 6 kV and Well cluster No. 58
The Customer: GazpromNeft Novy Port ООО (Ltd.) Execution period: July, 2016 — November, 2017
Substation 500 kV Tyumen. 500 kV Switchgear – bay No. 9; Disconnecting devices, 2 sets, RG(РГ)-500; Current transformer NDKM(НДКМ)-500
The Customer: FGS UES АО (JSC) — Branch of CIUS EES ОАО (JSC)-CIUS of Western Siberia Execution period: November, 2016 — December, 2016
Replacement of the bus system of OHTL 110 kV Vyazovskaya – Salka 1,2 on Substation 220 kV Vyazovskaya
The Customer: FGS UES PAO (JSC) – Main Power Networks of the Urals (MES Urala) Execution period: October, 2015 — January, 2016
Reconstruction of OHTL 220 kV Yaroslavskaya – Tutaev, OHTL 220 kV Yaroslavskaya – Tveritskaya. Incoming lines to Yaroslavskaya HEP (CCGT – 470 MW)
The Customer: FGS UES ОАО (JSC) — Main Power Networks of the Centre (MES Centra) Execution period: December, 2014 — December, 2016
Comprehensive technical upgrading and retooling of Substation 220 kV Levoberezhnaya
The Customer: FGS UES АО (JSC) — Branch of CIUS EES ОАО (JSC)-CIUS of Siberia Execution period: January, 2016 — July, 2017
Reconstruction of Substation No. 733 110 kV Bylovo, replacement of transformers 2х10 MVA by 2х40 MVA, reconstruction of 110 kV Switchgear
The Customer: MOESK ОАО (JSC) Execution period: November, 2015 — December, 2015
Reconstruction of Substation 220 kV Kalininskaya
The Customer: FGS UES АО (JSC) — Branch of CIUS EES ОАО (JSC) CIUS of the Urals Execution period: November, 2015 — December, 2015
«Kureyskaya HPP - Ust-Khantayskaya HPP. Workshop for heating and electrical networks of Thermal and electrical network enterprise in Dudinka. Construction of a new overhead line 6 kV from SDS-27 f.37 with the installation of Unit Transformer Substation-6 / 0.4 kV for power supply of TV and radio receiving and transmitting digital broadcasting equipment». Development of project and work documentation
The Customer: Norilsk-Taimyr Power Generating Company ОАО (JSC) (NTEK ОАО (JSC)) Execution period: August, 2015 — December, 2015
Reconstruction of OHTL sections 500 kV Yuzhnaya-Tagil; Reconstruction of OHTL 220 kV Ryabina- Yuzhnaya, Yuzhnaya -Pervouralskaya-1, Yuzhnaya - Pervouralskaya -2. Construction stage I.
The Customer: Fortum-Group ZAO (JSC) Execution period: August, 2015 - September, 2015
Construction of a double-circuit transmission line-6 kV and 2 modular packaged transformer substations. Engineering survey, development of work documentation
The Customer: Oblkommunenergo PAO (JSC) Execution period: July, 2015 - September, 2015
Power management system and Electric power fiscal metering system on the project: Substation 110/35 kV at Novy Port oil and gas field, with account of technical solutions of MIR Research and Production Association ООО (Ltd.)
The Customer: GazpromNeft Novy Port ООО (Ltd.) Execution period: July, 2015 — December, 2015
Reconstruction of Workshop No. 34 including the reconstruction of Box No. 6, Construction of a new transformer substation
The Customer: Tyumenskie Motorostroiteli ОАО (JSC) Execution period: August, 2014 — June, 2015
Pressure-tight oil pipeline at Novy Port oil and gas field – Mys Kamenny. Pipe string-2. Power supply system of 2 Substations 110 kV
The Customer: GazpromNeft Novy Port ООО (Ltd.) Execution period: May, 2015 — July, 2015
Buribaevskaya Solar Power Station 20 MW: Baimakskaya CPP (Stage 1), Yuldybaevskaya CPP (Stage 2) 10 MW
The Customer: Avelar solar Technology OOO (Ltd.) Execution period: May, 2015 — December, 2015
Technical upgrading of 500 kV Switchgear of Iriklinskaya GRES-plant (reconstruction of the shunting reactor bay 500 kV)
The Customer: FGS UES PAO (JSC) – Main Power Networks of the Urals (MES Urala) Execution period: November, 2014 — December, 2015
«Реконструкция ПС 220 кВ Острая (с заменой АТ 40 МВА и 3 МВ 220 кВ)». Разработка проектной документации
The Customer: FGS UES PAO (JSC) – Main Power Networks of the Urals (MES Urala) Execution period: November, 2014 — December, 2015
Technical retooling of Substation 110/ 35/ 6 kV Kalcha
The Customer: TyumenEnergo ОАО (JSC) Execution period: November, 2014 — March, 2015
Reconstruction of Workshop No. 34 including Box No. 6, construction of new cooling towers and a transformer substation
The Customer: Tyumenskie Motorostroiteli ОАО (JSC) Execution period: August, 2014 — June, 2015
Construction of Novy Port oil, gas and condensate field facilities. Gas-turbine power plant (GTPP)
The Customer: GazpromNeft Novy Port ООО (Ltd.) Execution period: December, 2013 — November, 2014
«Reconstruction of 110 kV outdoor switchgear with temporary rewiring of 110 kV overhead lines into replacement cells 19 ... 21 with the use of cable inserts as part of the title: «Reconstruction of the 500 kV Tyumen substation». Development of work documentation
The Customer: FGS UES PAO (JSC) – Main Power Networks of Western Siberia (MES Zapadnoy Sibiri) Execution period: December, 2013 — February, 2014
Development of Novy Port oil, gas and condensate field facilities. OHTL 110 kV. Substation 110/ 6 kV
The Customer: GazpromNeft Novy Port ООО (Ltd.) Execution period: February, 2014 — November, 2014
Work on adjusting the project documentation for the project: «Substation 220 kV Stroitelnaya»
The Customer: NIPIGAZ AO (JSC) Execution period: December, 2014 — December, 2016
Complex of works on the capital construction project of the Amur Gas Chemical Complex. Substation 500 kV AGHK
The Customer: NIPIGAZ AO (JSC) Execution period: December, 2014 — December, 2016
Complex of works on the project: «Construction of the 220 kV Ozernaya substation with two autotransformers 125 MVA each and 110 kV switchgear, construction of the 220 kV Chita - Ozernaya I and II circuits with an approximate length of 230 km, reconstruction of the 220 kV Chita substation»
The Customer: Ozernoye OOO (Ltd.) Execution period: July, 2020 - July, 2021
Complex of works on the project: «Construction of the 35/6 kV substation GOK and the branch OHTL 35 kV from the 35 kV overhead line Sosnovo-Ozerskaya-Gunda to the 35/6 kV substation GOK»
The Customer: Ozernoye OOO (Ltd.) Execution period: April, 2020 - February, 2021
Комплекс работ по разработке проектной документации по объектам: ЛЭП 220 кВ Таежная-Малмыж, ПС 220 кВ Малмыж и ПС 500 кВ Таежная
The Customer: «Amur Minerals» OOO (Ltd.) Execution period: April, 2020 - 2021
Execution of a complex of works on the project: «OHTL 220 kV Oznachennoe - Stepnaya (section from support 64 to the substation 220 kV Stepnaya) and the substation 220 kV Stepnaya with incoming lines 220 kV, Askiz, Republic of Khakassia»
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: March, 2020 - 2021
Implementation of the project: «Construction of a refueling complex of JSC AERO-Sheremetyevo»
The Customer: «AERO-Sheremetyevo» AO (JSC) Execution period: June, 2020 - January, 2021
«Upgrading of Izhevskaya CHPP-2»
The Customer: «ROTEK» AO (JSC) Execution period: September, 2020 - 2021
Implementation of a complex of works on the project: «Construction of waste water treatment facilities with sewerage networks in the villages of Termalny and Paratunka, Yelizovsky district of Kamchatka Territory» 2nd start-up complex
The Customer: Teplo Zemli АО (JSC) Execution period: March, 2020 - February, 2021
Project for the construction of the mine «Inaglinskaya», Inaglinsky GOK AO (JSC). Construction of the substation «Severnaya» 35/6 kV with incoming lines 35 kV (Kolmar OOO (Ltd.))
The Customer: Inaglinsky GOK AO (JSC) Execution period: January, 2021
Development of project documentation on the project: Gas Treatment Plant in the area of Ust-Luga settlement. Power distribution station 110 kV
The Customer: NIPIGAZ AO (JSC) Execution period: February, 2021.
Development of work documentation for the facilities: Substation 500 kV; OHTL 110 kV Amursky Gas Chemical Combine-MSDS-1; OHTL 110 kV Amursky Gas Chemical Combine - MSDS -2; OHTL 110 kV Amursky Gas Chemical Combine - MSDS-3; Substation 110 kV MSDS -1; Substation 110 kV MSDS -2; Substation 110 kV MSDS -3 on the Project: Amursky Gas Chemical Combine
The Customer: NIPIGAZ AO (JSC) Execution period: July, 2020 - October, 2021
Comprehensive reconstruction of substation 220 kV Zapadno-Sibirskaya
The Customer: Branch of CIUS EES АО (JSC) — CIUS of Siberia (CIUS Sibiri) Execution period: April, 2017 - 2021
Complex of works on 6, 8 10 stages on the project: «Reconstruction of the 220 kV Kalininskaya Substation»
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: January, 2020 - July, 2021
Novy Port gas and oil field. Engineering services
The Customer: GiprotyumenNeftegaz PAO (JSC) Execution period: February, 2020 - August, 2021
Implementation of a complex of works on the investment project: «Construction of the second 220 kV OHTL Minusinskaya master station - Kamala-1 with an approximate length of 445 km»
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: December, 2020.
Implementation of a complex of works on the project: «Substation 110/10 kV «SEZ Yelets 1» on the territory of SEZ «Lipetsk» in the Yeletsk district of the Lipetsk region»
The Customer: JSC «SEZ PPT «Lipetsk» Execution period: 17 November, 2020.
Development of project documentation for the reconstruction of the heat supply source of Baikalsk town (Irkutskaya Oblast, Slyudyansky district, the premises of Baikalskaya CHPP), Stage-I
The Customer: Administration of Baikalsk municipal settlement Execution period: December, 2018 – June, 2020
Implementation of a set of work in progress on the project: «Construction of 220 kV Sukhoi Log substation with a transformer capacity of 126 MVA, construction of a single-circuit 220 kV overhead line Peleduy - Sukhoi Log with an approximate length of 248 km, construction of two single-circuit 220 kV overhead lines Sukhoi Log - Mamakan with an approximate length of 169.9 km each»
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: May, 2019 — April, 2020
Comprehensive upgrading, retooling and reconstruction of the 500 kV substation Beskudnikovo for the needs of the branch of «FGC UES" PAO (JSC) - MES of the Center»
The Customer: FGS UES PAO (JSC) – Main Power Networks of the Centre (MES Centra) Execution period: December, 2018 – March, 2020
Construction of the 2nd OHTL 220 kV Minusinskaya master substation — Kamala-1, appr. length = 445 km.
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: November, 2019 — December, 2019
Execution of survey and design works for the construction of a 110 kV transmission line for connecting the substation of the Kamenskaya Wind Farm and the substation of the Sulinskaya Wind Farm to electrical networks within the construction project: «Kamensko-Krasnosulinskaya Wind Farm-Severnaya site» (VetroPark)
The Customer: The 2nd Wind Farm - Fund for Wind Power Engineering Development ООО (Ltd.) Execution period: April, 2019 — December, 2019
«OHTL 220 kV Peleduy - Sukhoi Log, OHTL 220 kV Mamakan - Sukhoi Log with substation 220 kV Sukhoi Log» OHTL 220 kV Mamakan-Sukhoi Log
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: June, 2018 – July, 2019
Substation 220 kV Zharki, OHTL 220 kV and reconstruction of Substation Novo-Krasnoyarskaya-220 kV to be renamed into Substation 220 kV Zharki. Amendments to work documentation
The Customer: Branch of CIUS EES АО (JSC) — CIUS of Siberia (CIUS Sibiri) Execution period: April, 2017 — August, 2019
Novy Port gas and oil field. Engineering services
The Customer: GiprotyumenNeftegaz PAO (JSC) Execution period: April, 2019 — January, 2020
Design of security zones on the project: «OHTL 220 kV Peleduy-Sukhoi Log, OHTL 220 kV Mamakan - Sukhoy Log with substation 220 kV Sukhoi Log». Working documentation
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: September, 2018 — November, 2018
«OHTL 220 kV Peleduy - Sukhoi Log, OHTL 220 kV Mamakan - Sukhoi Log with substation 220 kV Sukhoi Log» Substation 220 kV Sukhoi Log COMPLEX 1. Working documentation
The Customer: FGS UES PAO (JSC) – Main Power Networks of Siberia (MES Sibiri) Execution period: April, 2018 — October, 2018
Novy Port oil and gas field. Substation 110/6 kV PSP, Substation 110/10 kV, Substation 110/35 kV (gas-turbine power plant)
The Customer: GazpromNeft Novy Port ООО (Ltd.) Execution period: December, 2017 — December, 2018
OHTL 500 kV Voskhod - Vityaz
The Customer: Branch of CIUS EES АО (JSC) — CIUS of Siberia (CIUS Sibiri) Execution period: December, 2017 — January, 2018
«500 kV overhead line Rostovskaya NPP-Rostovskaya with the expansion of the 500 kV Rostovskaya substation (one 500 kV line cell). Amendments». Development of working documentation, field supervision
The Customer: FGS UES PAO (JSC) – Main Power Networks of the South (MES Yuga) Execution period: June, 2017 — February, 2018
Reconstruction of MSDS-220 (main step-down substation 220 kV) on the premises of the operating plant GazpromNeft-ONPZ АО (JSC)
The Customer: GazpromNeft0ONPZ АО (JSC) Execution period: April, 2016 — June, 2018
OHTL 220 kV Selikhino — Vanino with the installation of the 2nd Auto Transformer АТ on Substation 220 kV Vanino on the project: OHTL 220 kV Komsomolskaya – Sovietskaya Gavan’ (renamed on the basis of positive findings of Glavgosexpertiza of Russia into: OHTL 220 kV Komsomolskaya – Selikhino – Vanino)
The Customer: FGS UES PAO (JSC) – Main Power Networks of the East (MES Vostoka) Execution period: June, 2016 — December, 2018
Comprehensive technical upgrading and retooling of Substation 220 kV Levoberezhnaya (amendments)
The Customer: FGS UES АО (JSC) — Branch of CIUS EES ОАО (JSC)-CIUS of Siberia Execution period: January, 2016 - December, 2017
Reconstruction of 110 kV Switchgear within the project: Reconstruction of Substation 500 kV Tyumen
The Customer: FGS UES PAO (JSC) – Main Power Networks of Western Siberia (MES Zapadnoy Sibiri) Execution period: March, 2017 — September, 2017
Technical retooling of Substation 110 kV Evikhon for the project: Development of Vadelypsky oil and gas field. OHTL 35 kV connecting Substation Evikhon 110/ 35/ 6 kV and Well cluster No. 58
The Customer: GazpromNeft Novy Port ООО (Ltd.) Execution period: July, 2016 — November, 2017
Comprehensive technical upgrading and retooling of Substation 220 kV Levoberezhnaya
The Customer: FGS UES АО (JSC) — Branch of CIUS EES ОАО (JSC)-CIUS of Siberia Execution period: January, 2016 — July, 2017
Substation 500 kV Tyumen. 500 kV Switchgear – bay No. 9; Disconnecting devices, 2 sets, RG(РГ)-500; Current transformer NDKM(НДКМ)-500
The Customer: FGS UES АО (JSC) — Branch of CIUS EES ОАО (JSC)-CIUS of Western Siberia Execution period: November, 2016 — December, 2016
Replacement of the bus system of OHTL 110 kV Vyazovskaya – Salka 1,2 on Substation 220 kV Vyazovskaya
The Customer: FGS UES PAO (JSC) – Main Power Networks of the Urals (MES Urala) Execution period: October, 2015 — January, 2016
Reconstruction of OHTL 220 kV Yaroslavskaya – Tutaev, OHTL 220 kV Yaroslavskaya – Tveritskaya. Incoming lines to Yaroslavskaya HEP (CCGT – 470 MW)
The Customer: FGS UES ОАО (JSC) — Main Power Networks of the Centre (MES Centra) Execution period: December, 2014 — December, 2016
Reconstruction of Substation No. 733 110 kV Bylovo, replacement of transformers 2х10 MVA by 2х40 MVA, reconstruction of 110 kV Switchgear
The Customer: MOESK ОАО (JSC) Execution period: November, 2015 — December, 2015
Reconstruction of Substation 220 kV Kalininskaya
The Customer: FGS UES АО (JSC) — Branch of CIUS EES ОАО (JSC) CIUS of the Urals Execution period: November, 2015 — December, 2015
«Kureyskaya HPP - Ust-Khantayskaya HPP. Workshop for heating and electrical networks of Thermal and electrical network enterprise in Dudinka. Construction of a new overhead line 6 kV from SDS-27 f.37 with the installation of Unit Transformer Substation-6 / 0.4 kV for power supply of TV and radio receiving and transmitting digital broadcasting equipment». Development of project and work documentation
The Customer: Norilsk-Taimyr Power Generating Company ОАО (JSC) (NTEK ОАО (JSC)) Execution period: August, 2015 — December, 2015
Reconstruction of OHTL sections 500 kV Yuzhnaya-Tagil; Reconstruction of OHTL 220 kV Ryabina- Yuzhnaya, Yuzhnaya -Pervouralskaya-1, Yuzhnaya - Pervouralskaya -2. Construction stage I.
The Customer: Fortum-Group ZAO (JSC) Execution period: August, 2015 - September, 2015
Construction of a double-circuit transmission line-6 kV and 2 modular packaged transformer substations. Engineering survey, development of work documentation
The Customer: Oblkommunenergo PAO (JSC) Execution period: July, 2015 - September, 2015
Power management system and Electric power fiscal metering system on the project: Substation 110/35 kV at Novy Port oil and gas field, with account of technical solutions of MIR Research and Production Association ООО (Ltd.)
The Customer: GazpromNeft Novy Port ООО (Ltd.) Execution period: July, 2015 — December, 2015
Pressure-tight oil pipeline at Novy Port oil and gas field – Mys Kamenny. Pipe string-2. Power supply system of 2 Substations 110 kV
The Customer: GazpromNeft Novy Port ООО (Ltd.) Execution period: May, 2015 — July, 2015
Buribaevskaya Solar Power Station 20 MW: Baimakskaya CPP (Stage 1), Yuldybaevskaya CPP (Stage 2) 10 MW
The Customer: Avelar solar Technology OOO (Ltd.) Execution period: May, 2015 — December, 2015
Technical upgrading of 500 kV Switchgear of Iriklinskaya GRES-plant (reconstruction of the shunting reactor bay 500 kV)
The Customer: FGS UES PAO (JSC) – Main Power Networks of the Urals (MES Urala) Execution period: November, 2014 — December, 2015
«Реконструкция ПС 220 кВ Острая (с заменой АТ 40 МВА и 3 МВ 220 кВ)». Разработка проектной документации
The Customer: FGS UES PAO (JSC) – Main Power Networks of the Urals (MES Urala) Execution period: November, 2014 — December, 2015
Technical retooling of Substation 110/ 35/ 6 kV Kalcha
The Customer: TyumenEnergo ОАО (JSC) Execution period: November, 2014 — March, 2015
Reconstruction of Workshop No. 34 including the reconstruction of Box No. 6, Construction of a new transformer substation
The Customer: Tyumenskie Motorostroiteli ОАО (JSC) Execution period: August, 2014 — June, 2015
Reconstruction of Workshop No. 34 including Box No. 6, construction of new cooling towers and a transformer substation
The Customer: Tyumenskie Motorostroiteli ОАО (JSC) Execution period: August, 2014 — June, 2015
Construction of Novy Port oil, gas and condensate field facilities. Gas-turbine power plant (GTPP)
The Customer: GazpromNeft Novy Port ООО (Ltd.) Execution period: December, 2013 — November, 2014
«Reconstruction of 110 kV outdoor switchgear with temporary rewiring of 110 kV overhead lines into replacement cells 19 ... 21 with the use of cable inserts as part of the title: «Reconstruction of the 500 kV Tyumen substation». Development of work documentation
The Customer: FGS UES PAO (JSC) – Main Power Networks of Western Siberia (MES Zapadnoy Sibiri) Execution period: December, 2013 — February, 2014
Development of Novy Port oil, gas and condensate field facilities. OHTL 110 kV. Substation 110/ 6 kV
The Customer: GazpromNeft Novy Port ООО (Ltd.) Execution period: February, 2014 — November, 2014