OHTL 220 kV Selikhino — Vanino with the installation of the 2nd Auto Transformer АТ on Substation 220 kV Vanino on the project: OHTL 220 kV Komsomolskaya – Sovietskaya Gavan’ (renamed on the basis of positive findings of Glavgosexpertiza of Russia into: OHTL 220 kV Komsomolskaya – Selikhino – Vanino)

The Customer:

FGS UES PAO (JSC) – Main Power Networks of the East (MES Vostoka)

Виды работ:

  1. Разработка и корректировка рабочей документации
  2. Авторский надзор

Сроки реализации: June, 2016 — December, 2018

Пролистать наверх