UralProjectEngeneering will carry out design and survey works (project documentation, work documentation) for the project: “The construction of Substation 220 kV Sukhoy Log with transformer capacity of 126 MVA, the construction of one-circuit OHTL 220 kV Peledui-Sukhoy Log of appr. length equal to 248 km, the construction of 2 one-circuit OHTL’s 220 kV Sukhoy Log – Mamakan of appr. length equal to 169.9 km each”.

The project will be carried out within the Comprehensive Program for upgrading and expansion of the trunk infrastructure developed by the Russian Government in light of May 2018 presidential decrees. The Peledui energy ring will make it possible to eliminate the power system deficiency in the north-eastern part of Irkutsk Oblast and to set up additional links between the western energy district of Yakutia and the Unified National Power Grid.

The Customer: Energomost OOO (Ltd.)